Dalton Elementary School
-
Overview: Contractor bids were opened in Feb. 2018, with the goal of completing the bulk of the updates in September 2018. A new school parking lot was added in fall 2017.
Lead architect on this project is Cory Trapp (Longwell + Trapp) who previously worked with our district on the earlier Lakes Middle School remodel.
Firm: Longwell + Trapp l View Proposed Plans
Use link above to view the proposed plans. *Note that this proposed plan is tentative and may change due to bidding or other project issues.*
Background: The Board of Trustees for Coeur d'Alene Public Schools accepted the construction bids for the expansion of Dalton Elementary School in February 2018. Dardan Enterprises, Inc. of Post Falls submitted the lowest of two bids, at $2,718,000, for the Dalton project. The expansion will include three new classrooms, a newly designed art room, a newly designed media center, and a new stage and music room attached to the gymnasium. Longwell + Trapp provided the design.
Because bids were higher than anticipated, some non-essential components of the projects need to be withdrawn to ensure the work can be completed within budget. When the projects are completed, the district will review if contingency funds are sufficient to complete the components withdrawn from the plan. The general construction budget is $2.3 million for the Dalton project. The unbudgeted contingency fund is $315,000.
Highlights:
- Two new classrooms
- New art room
- New music room/stage
- New media center
- New staff bathrooms
- Reconfigure parking lot
Before Construction Photos - Dalton
Latest Update:
-
August 2018
Classroom finishing work begins, new stages takes shape.
------------------------
July 2018
Walls rise on new classrooms, stage.
------------------------
June 2018
Construction kicks into full swing following end of school year.
------------------------
Spring 2018
Sire work begins for stage/music room addition.
------------------------
February 2018
Construction bid awarded to Dardan Enterprises, Inc.
------------------------
June 2017
Pre-construction work started by district maintenance.
------------------------
June 13, 2017
Bond Sale closed with a 2.47% rate, lower than expected, resulting in 2.5M interest savings.
------------------------
May 1, 2017
Architect Longwell +Trapp selected and approved by board.
------------------------
April 7, 2017
Start accepting bids for architectural firms.
------------------------
March 14, 2017
The Levy & Bond pass.